Gemini North Semester 2014B
The semester calendar shows multi-instrument queue nights, scheduled classical runs and engineering or commissioning blocks. Instruments potentially usable on queue nights are
indicated by the colored-horizontal bands (see color key below). Note: Rapid ToO PIs should always check the "what's available now" pages that are linked from the contents list for
the most up-to-date information. Scheduled classical runs are indicated in the instrument's row by the last characters of the GN-2014B-É program ID number.
Engineering or commissioning that involves one or more instruments is shown in the relevant instrument row(s). Of the order of 4 engineering nights will be scheduled in queue. 
New and full moon dates are shown.
Key: GMOS   NIRI   Visiting   Altair  
NIFS   GNIRS   eng./commis.  
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 total
August GMOS                                           Priority Visitor LP-1             August
  GNIRS/NIRI                                                                 
9 full NIFS/TEXES                                                              
24 new Altair/other                                                                
 
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 total
September GMOS                                                             September
  NIRI                                                              
7 full NIFS                           Shutdown                              
22 new Altair/other       LGS                                                      
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 total
October GMOS                                                               October
  NIRI/GNIRS                                                                
7 full NIFS/NIRI                                                                
22 new Altair/other       LGS                                                      
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30   total
November GMOS           November
  GNIRS                                                          
5 full NIRI/NIFS                                                 C-1              
21 new Altair/other           LGS                                                
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 total
December GMOS                                             December
  GNIRS                                                  
5 full NIRI/NIFS   C-1                                                        
20 new Altair/other           LGS                                                    
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 total
January GMOS             Priority Visitor LP-3                     January
  GNIRS/NIRI                                                                
3 full NIFS/NIRI               C-2                    
19 new Altair/other                                               LGS through Feb 2  
3-Oct-14   0