Gemini South Semester 2007A |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
PDF Version
The semester calendar shows multi-instrument queue
nights, scheduled classical runs and engineering or commissioning blocks.
Instruments potentially usable on queue nights are |
|
|
|
|
|
|
indicated by the coloured-horizontal bands (see
color key below). Note: ToO PIs should always check the "what's
available now" pages that are linked from the contents list for |
|
|
|
|
|
|
|
the most up-to-date information. Scheduled classical
runs are indicated by the instrument name (or an abbrieviated version) and
the last characters of the GS-2007A-É program |
|
|
|
|
|
|
ID number. Engineering or commissioning that
involves one or more instruments is shown in the relevant instrument row(s).
New and full moon dates are shown. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Key: |
|
GMOS |
|
|
|
GNIRS |
|
|
|
T-ReCS |
|
|
|
engineering |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Phoenix |
|
|
|
NICI |
|
|
|
|
FLAMINGOS-2 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
15 |
16 |
17 |
18 |
19 |
20 |
21 |
22 |
23 |
24 |
25 |
26 |
27 |
28 |
29 |
30 |
31 |
|
February |
GMOS |
|
|
|
|
|
|
|
queue |
queue |
|
|
|
queue |
|
|
|
|
|
|
|
February |
|
GNIRS |
|
|
|
|
|
|
|
queue |
|
queue |
|
|
|
queue |
|
|
|
|
|
|
|
|
1 full |
T-ReCS |
|
|
|
|
|
|
|
queue |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
FLAMINGOS-2 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
17 new |
NICI |
|
|
|
|
|
|
|
|
|
|
|
NICI installation |
NICI comm. |
|
|
NICI
comm. |
|
|
|
|
|
|
other |
Phoenix
C8+C4* |
C4* |
C8+C3* |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Ps |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
March |
GMOS |
|
|
|
|
|
|
queue |
|
|
|
|
GS-2007A-C-6 |
queue |
|
|
|
queue |
|
|
|
March |
|
GNIRS |
|
|
|
|
|
|
queue |
GS-2007A-C-9 |
|
|
|
queue |
|
|
|
queue |
|
|
|
|
3 full |
T-ReCS |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
queue |
|
|
|
|
|
|
queue |
|
|
|
|
|
FLAMINGOS-2 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
18 new |
NICI |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
other |
C2 |
C7 |
C1 |
Phoenix
C5 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
April |
GMOS |
queue |
|
|
|
queue |
|
GS
Telescope Shutdown |
Eng. Contingency/queue |
|
|
|
April |
|
GNIRS |
queue |
|
|
|
queue |
|
GS
Telescope Shutdown |
Eng. Contingency/queue |
|
|
|
|
2 full |
T-ReCS |
queue |
|
|
|
queue |
|
GS
Telescope Shutdown |
Eng. Contingency/queue |
|
|
|
|
|
FLAMINGOS-2 |
|
|
|
|
|
|
|
|
GS
Telescope Shutdown |
Eng. Contingency/queue |
|
|
|
|
17 new |
NICI |
|
|
|
|
|
|
|
|
GS
Telescope Shutdown |
Eng. Contingency/queue |
|
|
|
|
|
other |
|
|
|
|
|
|
|
|
GS
Telescope Shutdown |
Eng. Contingency/queue |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
May |
GMOS |
queue |
|
|
|
|
|
|
|
|
|
|
|
queue |
|
|
|
|
|
|
queue |
May |
|
GNIRS |
out of
service |
|
2, 31 full |
T-ReCS |
queue |
|
Q-38 |
|
|
|
|
|
|
|
|
queue |
|
|
|
|
|
|
queue |
|
|
FLAMINGOS-2 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
16 new |
NICI |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
other |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
June |
GMOS |
|
|
|
|
|
queue |
|
|
|
|
|
|
|
|
queue |
|
|
|
|
|
|
|
|
|
|
June |
|
GNIRS |
out of
service |
|
30 full |
T-ReCS |
|
|
|
|
|
queue |
|
|
FLAMINGOS-2 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
14 new |
NICI |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
other |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
July |
GMOS |
|
|
queue |
|
|
|
|
|
queue |
|
|
|
|
|
|
queue |
maintenance |
|
|
July |
29 full |
T-ReCS |
|
|
|
queue |
|
|
|
|
|
|
queue |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Phoenix |
|
|
|
|
preventative maintenance |
mounted on telescope |
|
|
|
|
|
queue
backup |
|
14 new |
NICI |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
mounted |
|
|
day
work |
NICI commissioning |
|
|
other |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
15 |
16 |
17 |
18 |
19 |
20 |
21 |
22 |
23 |
24 |
25 |
26 |
27 |
28 |
29 |
30 |
31 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
* Phoenix notes, Feb-Mar: Some Phoenix
programs will share nights. On the nights of February 1-3, C8 will use the
first 1/3 of the night, and C4 will use the latter 2/3. C4 has the entire
night of February 4. |
|
Similarly the nights of February 5-7
wil be shared by C8 and C3, with C8 allocated the first 1/3 of the night and
C3 the latter 2/3. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
* NICI notes: NICI commissioning and
campaign science will require removal of TReCS. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
* FLAMINGOS-2 notes: FLAMINGOS-2
commissioning will not start in 2007A. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
* Engineering contingency nights reserved
for April 25-28 will revert to queue if not needed. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Last updated 5-July-2007 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|