Gemini South Semester 2010B

PDF Version

The semester calendar shows multi-instrument queue nights, scheduled classical runs and engineering or commissioning blocks. Instruments potentially usable on queue nights are
indicated by the colored-horizontal bands (see color key below). Note: ToO PIs should always check the "what's available now" pages that are linked from the contents list for
the most up-to-date information. Scheduled classical runs are indicated by the last characters of the GS-2010B-É program ID number.
Engineering or commissioning that involves one or more instruments is shown in the relevant instrument row(s). New and full moon dates are shown on the left.
Key: GMOS   T-ReCS   engineering   Canopus     Commissioning only
Phoenix   NICI     F-2     Commissioning only GSAOI     Commissioning only
v1.3 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
August GMOS-S                                                               August
10 new NICI                                       C-5           Campaign          
24 full Phoenix/Canopus                                                                
  T-ReCS   C-7 *                                                       C-4  
  Flamingos-2  
  GSAOI/other                                                                
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
September GMOS-S                                                               September
8 new NICI                                     Campaign             engineering shutdown      
23 full Phoenix/Canopus                                                                
  T-ReCS                                                                
  Flamingos-2            
  GSAOI/other                                                                
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
October GMOS-S                                                               October
7 new NICI       engineering shutdown                                           Campaign          
23 full Phoenix/Canopus                   M1 Coating, Helium line repairs, other maintenance                   contingency                        
  T-ReCS                                                                
  Flamingos-2                                              
  GSAOI/other                                                                
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
November GMOS-S                                                               November
6 new NICI                                   Campaign                        
21 full Phoenix/Canopus                                             C-8   C-1            
  T-ReCS     Q-12 in queue                                 C-9                  
  Flamingos-2  
  GSAOI/other                                                                
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
December GMOS-S           C-2                                                   December
5 new NICI                                             Campaign                
21 full Phoenix/Canopus                                         C-3 **                    
  T-ReCS                                                                
  Flamingos-2  
  GSAOI/other ***                                                              
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
January GMOS-S       C-6           ^ ^                                         January
4 new NICI                     uplooking port                                
19 full Phoenix/Canopus         mount Canopus                                        
  T-ReCS             LGSF commissioning  
  Flamingos-2          
  GSAOI/other                         mount GSAOI                                  
    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31  
Notes:
^Jan 11 shutdown for GeMS installation activity; Jan 10 may be impacted as well
NICI Campaign nights are adjustable and will vary between 1 to 5 nights each month.
* 1/2 nights  
** 1/2 nights  
*** 2011A Software Release scheduled
Updated 3 Jan 2011, BR
Updated 16 Dec 2010, BR
Updated 10 Nov 2010, BR
Updated 08 June 2010, SJM
Updated 19 May 2010, BR
Created 11-Feb-2010 BR