Large Program Queue Summary : Semester 2014B GN |
The queues shown in the tables below summarise the programs that constitute the "Large Program Queue" on GN.
This report is generated daily (see the bottom of the page for the current timestamp). The pages linked via Completion Status are updated approximately every 4 hours. Note that the completion fraction may change as the time accounting is adjusted during the quality assessment process.
The assigned support staff (Gemini Contact Scientists and National Office staff) for each Gemini North ODB and Gemini South ODB program are listed in the interactive 'snapshots' of the Observing Database (ODB).
GN Large Program Queue | ||||||
Ref # | PI | Partner | Title | Instrument | Hours allocated |
|
GN-2014B-LP-1 | Fraser | LP | COL-OSSOS: COLours for the Outer Solar System Origins Survey | GMOS / NIRI | 49.00 | |
Execution Status: complete | Dates Taken: 20140822 20140823 20140824 20140825 20140826 20140827 20140828 20140829 20140830 20141022 20141025 20141027 20141028 20141029 |
Completion Status:
|
||||
GN-2014B-LP-2 | Kasliwal | LP | Rapid Spectroscopy of Elusive Transients and Young Supernovae | GMOS | 27.10 | |
Execution Status: RToO | Dates Taken: 20140820 20140831 20140926 20141005 20141012 20141015 20141023 20141107 20141119 20141129 20150131 |
Completion Status:
|
||||
GN-2014B-LP-3 | Werk | LP | Where Accretion Meets Feedback: A Galaxy Redshift Survey in HST/COS Quasar Fields (North) | GMOS | 18.40 | |
Execution Status: complete | Dates Taken: 20141117 20141121 20141127 20141130 20141201 20141221 20141222 20150114 20150115 20150116 20150117 20150118 20150119 20150121 20150128 20150204 20150409 20150414 20170428 |
Completion Status:
|
Last updated on: 24 Jul 2020 17:42:13 GMT