Science Operations Announcements

GMOS-S optical maintenance

July 27th, 2018

GMOS-S came off the telescope on July 18, and after preliminary masurements on the CP instrument lab, the work for the collimator service started this week with the removal of the masks frame and its supporting structure, in order to free the way for the collimator removal.

GN Laser Schedule

June 20th, 2018

Engineering work on the new Gemini North Laser Guide Star system is taking longer than anticipated and it is not yet clear whether commissioning will take place in Semester 2018B. Therefore, LGS programs have not been included in the 2018B queue and National TACs looked for opportunities to convert LGS+P1 programs to IQ20+P2. If the laser is commissioned within 2018B it will be offered via Fast-Turnaround.

GS ODB back online

June 12th, 2018

The GS Observing Database is available today after the generator power was restored yesterday afternoon (commercial power is still down). The recovery of the rest of the systems is ongoing. Parts of the dome are still covered with large amounts of ice and it is expected that it will take a few days to be cleared. 

ODB offline due to winter storm

June 11th, 2018

Due to a general power outage affecting Cerro Pachon last night, all equipments on CPO are out of service, including the datacenter. Due to this the ODB is not available until further notice.
Engineering staff are working with NOAO operations to gain access to the summit and restore power as soon as possible.

 